Budget Speech para. 34: "In this regard, the “Nilwala Eliya” model park and mega zone will be established on the left bank of the Nilwala river in Matara." Allocation Revised: According to the progress report received, the budget allocation has been revised from 1,500 million to LKR 690 million.
  • Allocation (Rs. Mn)1,500
  • SectorIndustry & Commerce
  • Ministry / Government Institution : Ministry of Megapolis and Western Development

Openness Tracker

Open

Information on progress was obtained through the action plan and progress report made available on the website of the responsible government agency. Further, information was also provided in response to the request for information filed under the Right to Information Act No 12 of 2016 and a request made by email to the responsible government agency.

Progress Tracker

Poor

Based on the information made available, progress as at 31 December 2018 was assessed as 10% of the target set for 2018. Progress was determined as an average of the progress of all the activities under the promise since separate allocations for the activities were not provided. For two of the four activities under the promise, no progress was reported and was assumed to be 0%.

Sources of Information

  • Budget Tracker - Website Website
  • Budget Tracker - Website Over the counter
  • Budget Tracker - Website RTI