Upliftment of Sugathadasa outdoor stadium 

Budget Speech para. 190: "The pavilion and the tracks at the Sugathadasa Outdoor Stadium will also be upgraded to international standards." Allocation Revised: The allocation for this promise has been revised from LKR 1,200 million to LKR 1,398 million.
  • Allocation (Rs. Mn) :  1,200
  • Sector :  Youth & Women
  • Ministry / Government Institution :  Ministry of Provincial Councils, Local Government and Sports

Openness Tracker

Uncooperative

Information was obtained through (i) the 'Progress of development projects and programmes as at 31st March 2018' Report published online by the Department of Project Management and Monitoring; and (ii) the Action Plans, Financial Plan and Progress Report received from the responsible agency in response to a request under the RTI Act. However, information in response to the request was obtained after filing an appeal.

Progress Tracker

Lagging

Some activities under the promise have been inititated. However, progress for the first six months falls short of target. Based on information made available, progress as at 30 June 2018 (weighted by allocation) was 23%, behind the target (weighted by allocation) of 64%.

Sources of Information

  • Budget Tracker - Website Website
  • Budget Tracker - Website RTI